Planning and Status |
Reforms for Strengthening T&D System |
(After the formation of CSEB up to
March - 2024) |
S.N. | Name of Works |
Status as on
March 2023
|
Year
2023-24
Achievement
|
Status as on
March - 2024
|
1
| New 33/11 KV Sub-Station |
1104
|
57
|
1161
|
| (a) Additional 33/11 KV Power X'mers |
721
|
77
|
798
|
| (b) Augmentation of 33/11 KV Power X'mers |
1013
|
76
|
1089
|
2
| New Distribution Transformers under ND Schemes |
44336
|
7859
|
52195
|
3
| Augmentation of Distribution Transformers Under ND Schemes |
16048
|
2395
|
18443
|
|
|
|
|
|
|
|
|
|
|