Planning and Status |
Reforms for Strengthening T&D System |
(After the formation of CSEB up to
November - 2021) |
S.N. | Name of Works |
Status as on
March 2021
|
Year
2021-22
Achievement
|
Status as on
November - 2021
|
1
| New 33/11 KV Sub-Station |
1073
|
9
|
1082
|
| (a) Additional 33/11 KV Power X'mers |
592
|
47
|
639
|
| (b) Augmentation of 33/11 KV Power X'mers |
895
|
22
|
917
|
2
| New Distribution Transformers under ND Schemes |
33985
|
2159
|
36144
|
3
| Augmentation of Distribution Transformers Under ND Schemes |
13815
|
211
|
14026
|
|
|
|
|
|
|